References
SunPower Engineering Sdn Bhd products are known in every continent in the world and with our comprehensive distributor network we can satisfy customers needs right across the globe. Please click on the table below and you will get information about the concrete project. The projects are indexed by country and by product.
International
1. Casino,Preah Sihanouk (Cambodia)
A Synchronizing Panel for SV World Casino, Cambodia
- A synchronizing system with capacitor bank was designed for SV World Casino in Cambodia.
- To overcome the local’s unstable mains power supply, the system was specially customized for 2 gen sets synchronizing with the mains, to decrease further power interruption when the mains re onlined.
- Used of IG-NTC-BB controller along with InteliVision 5 color display packages and IM-NT controllers
- Testing and commissioning was carried out by Sunpower Engineering Sdn Bhd & WCL Engineering
2. Iraq Temporary Power Plant (Iraq)
- Synchronizing panel for 17 Caterpillar generators.
- Used 17 sets of IG-NT-BB controller c/w InteliVision 5 color display packages and 2 IM-NT controllers.
- Designed for connecting three groups of generators.
- Remote communication with local bridge and Internet Bridge are provided.
- Testing and commissioning will be carried out by Expet Control and Sunpower Engineering & Ent. together in Iraq.
3. Oil & Gas Company
Wheatstone Project, Chevron:
- New synchronizing panel designed for single HT MTU generators and two incoming mains.
- Used one set of IG-NTC controller with two IM-NT-BB controllers and 17” touch screen module.
- Testing and commissioning was carried out by Andeli Switchgear Sdn. Bhd. and Sunpower Engineering & Ent.
- System was delivered by August 2013
4. Bulan Island (Indonesia)
Synchronizing & Load Sharing System for Temasek Pig Farm, Bulan Island, Indonesia.
- System consisted of three Cummins generating sets.
- Three sets of IG-NT-BB package is applied.
- Power management is applied to enable load demand starting/stopping of generators.
- System is delivered by Static Power Pte. Ltd. From Singapore. Tested and commissioned by Sunpower Engineering & Ent. on December 2012.
5. Makaki (Philipines)
Synchronizing & Load Sharing System for Mayniland Water Treatment Plant, Makati, Philippines.
- System consisted of two Mitsubishi generating sets.
- 2 sets of IG-NT-BB controller with InteliVision 8 are applied.
- Power management is applied to enable load demand starting/stopping of generators.
- Integrated with 17inch touch screen together with third party SCADA system for remote monitoring function.
- Panel is made by Static Power Pte. Ltd. and delivered on October 2012.
6. Kudahithi Resort (Maldives)
Synchronizing & Load Sharing System for Kudahithi Resort, Maldives.
- System consisted of three Cummins generating sets.
- 3 sets of IG-NT-BB controllers and InteliVision 5 are applied.
- Power management is applied to enable load demand starting/stopping of generators.
- Panel is delivered by Static Power Pte. Ltd. and was commissioned by Sunpower Engineering & Ent. on December 2012.
7. Syang Hong Ltd (Vietnam)
Upgrading Project for Syang Hong Ltd., Vietnam
- Upgrading the existing synchronizing panel with old controllers to advanced style using comprehensive synchronizing controller with 8” color display.
- Consisted of two Mitsubishi generating sets and two Caterpillar generating sets.
- The job is carried out by Sunpower Engineering & Ent. on January 2013.
8. Perth Market City (Perth, Australia)
Start-Up Synchronizing System for Perth Market City, Perth – Australia:
- The system consisted of three Mitsubishi generating sets with 22kV transformers.
- 3 sets of IG-NT-BB controllers and InteliVision 5 displays are used.
- Start-Up Synchronization system is utilized, where the system started with ACB closed before generators are cranked up and excited.
- The system is delivered on January 2015.
Local / Domestic
1. Malaysia Utility Company (Bangsar, Kuala Lumpur)
Synchronizing Twin Mobile Genset fror Malaysia Utility Company
- The first synchronizing project for twin Scania 500 KVA mobile genset
- Using InteliGen NT controller
- Power management applied both generators will take turn upon 8 hours of operation
- Testing and commissioning by Sunpower Engineering Sdn BhdDelivered on October 2019
2. TBCP Platform (Kemaman, Terengganu)
3. Malaysia Skycraper (Kuala Lumpur)
Synchronizing System at one of Skyscraper building in Kuala Lumpur
- At this building, there are two 11 kV emergency generator sets on each tower separated with two bus tie breaker in between.
- The previous synchronizing system used Allen Bradley PLC system which has lasted for 20 over years. However, some of the functions are not well operated anymore.
- The entire synchronizing of all four generator sets has been upgraded with ComAp’s controllers of IG-NTC-BB controller along with InteliVision 8 color display packages including a remote monitoring system at each tower.
- Testing and commissioning was carried out by Sunpower Engineering Sdn Bhd & WCL Engineering.
4. Government Building (Putrajaya)
5. Malaysia Southern Port ( Johor)
6. Semiconductor factory (Kulim)
Start-up Synchronizing for Semiconductor Factory in Kulim
- The factory requires to have fast emergency backup power supply when mains failure occurs
- Sunpower Engineering Sdn Bhd have introduced and implemented Start up Synchronizing system for five 2200 kVA, 6.6 kV Mitsubishi generator sets. With Start-up Synchronizing system, emergency back up supply will be available in 15 seconds
- Used IG-NT-BB controller along with InteliVision 8 color display packages and 2 IM-NT controllers.
- Testing and commissioning was carried out by Sunpower Engineering Sdn Bhd & WCL Engineering.
7. Oil & Gas Offshore Platform (Sarawak)
Marine Application for Oil & Gas Offshore Platform
- Synchronizing between a 1250 kVA MTU emergency diesel gen-set and gas turbine.
- Used of IG-NTC-BB controller along with InteliVision 8 color display packages and equipped with Schneider’s SEPAM 80 protection relay.
- Testing and commissioning was carried out by Sunpower Engineering Sdn Bhd & WCL Engineering
8. Research & Development (Selangor)
9. Gua Musang Hospital (Gua Musang, Kelantan)
10. UPS Company (Kuala Lumpur)
11. Rental Genset Company ( Shah Alam, Selangor)
Synchronizing Panel for Rental Genset, KLKB
- Express Mission Rental Genset
- Synchronizing of 2 Cummins generator set
- Using the new InteliGen 200 controller
- Testing and commissioning by Sunpower Engineering Sdn Bhd
- Currently 6 in total synchronizing generator set carried out by Sunpower Engineering Sdn Bhd for this company
12. Putrajaya (Kuala Lumpur)
Upgrading Job for Putrajaya Synchronizing Panel
- Upgrading of existing synchronizing panel for 2 Dorman generators.
- The existing panel is using very complicated load sharing modules and was failed to synchronize two Dorman generators.
- The existing panel is upgraded with two sets of IG-NT package.
- The system is tested and delivered by May 2012.
13. Alor Gajah Hospital (Alor Gajah, Melaka)
- Synchronizing panel for 2 Volvo Penta generators.
- Used two set of IG-NT GC packages plus two IM-NT controllers.
- The application is designed for synchronizing system of two generators and reverse/passive synchronizing with two incoming mains/transformer incomers.
- Testing and commissioning was carried out by Sunpower Engineering & Ent.
- System was delivered by early 2012
14. Alstom Power Plant (Manjung, Perak)
15. Sunway Pinewood Studio (JB, Johor)
16. Strand Mall (Kota Damansara, Selangor)
17. Beaufort, Sabah
18. UNITEN, Bangi (Selangor)
Synchronizing Panel for UNITEN, Bangi, Selangor.
- System consisted of two Volvo generating sets and standby load bank.
- 2 sets of InteliCompact MINT controllers and accessories were applied.
- Power management is applied to enable load demand starting/stopping of generators.
- Coupled with manual synchronizing and load sharing system.
- The system is meant for both Auto and Manual system: When Auto mode is selected, only controller is functional with auto starting of gen-sets and breaker closing/opening; When Manual mode is activated, only push buttons and trimmers are concerned for synchronization purpose. It is connected to load bank for load test purpose.
- The system is delivered by Wengcon company.
19. Army Camp (Malaysia)
20. Mid Valley Megamall (Kuala Lumpur)
Upgrading of Synchronizing Panel for Mid Valley Megamall, Kuala Lumpur.
- Upgrading the existing synchronizing panel with PLC system to advanced style using comprehensive synchronizing controller IG-NT-BB with 8” color display.
- Consisted of four Mitsubishi generating sets with two bus-tie breakers located in north and south court of megamall.
- 4 sets of IG-NT-BB controllers with InteliVision 8 modules are used.
- The panels are delivered on June 2015.
21. Industrial Training Institute (Sarawak)
Synchronizing & Load Sharing System for Industrial Training Institute, Sarawak.
- System consisted of two Cummins generating sets.
- This system used two IG-NT GC controllers for both generating sets with redundant manual synchronizing system that enable fully manual synchronizing of generators bypassing controller in case of controller failure.
- Power management is applied to enable load demand starting/stopping of generators.
22. Connaught Bridge (Klang)
23. Bukit Trigg Telekon Tower (Sandakan)
Synchronizing & Load Sharing System for Bukit Trigg Telekom Tower, Sandakan
- System consisted of two Caterpillar generating sets.
- 2 sets of IC-NT MINT controller with accessories are applied.
- Power management is applied to enable load demand starting/stopping of generators.
- The panel is also come with manual synchronization system that overrides the auto synchronizer when any failure of controller is happened.
- Panel is delivered on November 2015.
24. ICON City Mall (Petaling Jaya)
Synchronizing & Load Sharing System for ICON City Mall, Petaling Jaya.
- System consisted of two diesel generating sets.
- 2 sets of IG-NT MINT controller with accessories are applied.
- Power management is applied to enable load demand starting/stopping of generators.
- The panel is also come with manual synchronization system that overrides the auto synchronizer when any failure of controller is happened.
- Panel is delivered on February 2016.
25. Serdang Hospital (Serdang)
Upgrading Project for Serdang Hospital, Serdang.
- Upgrading the existing synchronizing panel with old controllers to advanced style using comprehensive synchronizing controller – IG-NT GC module.
- The system is consisted of three Caterpillar generating sets.
- One of the IG-CU controller is malfunctioned, while the other two are still working. Therefore, the faulty controller is replaced with IG-NT GC controller with NT Converter to communicate with the two older version controller.
- The job is carried by Sunpower Engineering & Ent. on May 2016.
26. KPJ Hospital (Seremban)
Synchronizing & Load Sharing Panel for KPJ Hospital Seremban.
- System consisted of one older Dorman generating set and a brand new Perkins generating set.
- 2 sets of IG-NT MINT controller with accessories are applied.
- Power management is applied to enable load demand starting/stopping of generators.
- Panel is delivered on April 2016.
27. KD Indera Sakti
Synchronizing Panel for Marine Generating Sets, KD Indera Sakti.
- The system is consisted of 3 MAN Diesel generating sets comes with ID-DCU Marine controllers.
- This synchronizing panel used 3 IG-NT Marine controllers and InteliVision T2 touch screen display for showing all engine data from ID-DCU Marine controllers and AC measurement from IG-NT GC controllers.
- The system is delivered on August 2015.